A test package “coming back” is not the same as a hydrotest “failing”

· Erman Demirel · 1 min read

On site, two separate events are described in one sentence: "the package came back". One happens before water goes in (missing document, old isometric revision, open punch), the other under pressure (leak). Different causes, different costs, different denominators.

I looked: I could not find a combined rate for failed hydrotests or returned packages on B31.3 plant projects; other tools gave the same result. The verified example I found is a single case: two leaks in a newly installed 12-inch 304 stainless line at hydrotest, caused by microbiologically influenced corrosion (MIC), not a weld defect. The total number of joints tested is not stated, so no rate follows.

Another case: in Kuwait, in an underground composite (GRE) gas line, a joint near the valve pit and a tee leaked; the paper lists non-compliance with manufacturer recommendations, insufficient support in the pit, and a tee manufacturing defect, and the supply of the large-diameter tee delayed the project by 6 months (not metallic pipe).

At an NGL plant, with re-planning, 75.6% of packages were completed and approved by the time panels arrived; this is a completion rate, not a rejection rate.

Lesson: classifying "leak = bad weld" may be wrong; investigation is needed. The cost of a repeat test cannot be given as one number either; it has components: draining, repair, re-examination, refilling, re-mobilization, waiting on the critical path. You can price them from your own records.

Four numbers are enough to measure: packages submitted for readiness, returned at first submission, actually pressurized, leaked at first test. For each return and leak, the cause and the duration. Without these numbers, giving a percentage would mislead.

Sources: Mahajanam et al. (2022) failure analysis; Gunasekaran, NDE 2019 (CP-312); Ibrahim, SPE 2017 (OnePetro); West test package specification; Aramco/OGN.

Related articles

Do you know your weld repair rate?

The industry survey says 1-3%. Most teams do not know what a repair costs them. The figures, their limits, and how to find your own number.

Sep 30, 2026 · 2 min read

In material traceability, the error is usually at the installation, not the certificate

The “wrong material rate” does not reduce to one number. The figures found measure different things; the pattern in documented incidents is common.

Sep 30, 2026 · 1 min read

The honest answer to “how many documents are lost at handover?”

We could not find a measured rate for the percentage of documents lost at handover. What we found, what we did not, and a better measure.

Sep 30, 2026 · 1 min read